Ammonia Chilling Plant, Cornwall
Pipework Inc has recently completed a fast track installation of an ammonia chilling plant in Cornwall.
Pipework Inc was asked to intervene after the original contractor was unable to meet the project specifications for such an installation. This resulted in the cutting out and re welding of some 70, 12”,10”,8” positional butt welds. These alteration were completed by our coded welders. PED regulations were implicated and followed rigorously.
The practical completion date did not move to allow for this period of alterations and so we fast tracked the plant room and remaining roof Pipework in order for the client to remain on schedule.
The practical completion date did not move to allow for this period of alterations and so we fast tracked the plant room and remaining roof Pipework in order for the client to remain on schedule.